Melksham HUB Key Milestone Dates

 

Melksham Hub Café is a community rail initiative by TransWilts Community Interest Company. It is a not for profit organisation any surplus from the activities at the Melksham Hub will be invested in the local community. Read more


October 24th Progress

The month of October shows the substantial progress that has been made with most of the car park and exterior work now completed. Refurbishment of the cafe building interior shell is almost complete with brand new services, double glazed windows and doors. Our contractors have done a fantastic job!Read more


Hub Progress - 6th October

Yesterday (6th October) we visited the Melksham Hub site.

Read more


Melksham Hub Progress - September

We visited the Melksham Hub site today (8th Sept).

Read more


Platform Upgraded with Destination Indicators

GWR have installed train destination indicators as part of the Melksham Station Masterplan upgrade.

Read more


Contractors on Site - Progress Pictures 22 July 20

The site groundworks are taking shape and the site has been cleared.

Read more


Car Park Tidy Up has Started

TransWilts volunteers have started to tidy up the existing car park which has not received any attention for some time. The litter includes evidence of anti-social activity.Read more


Contractors meet with Designer to finalise work scope 20th July to 28th August

Final measurements made and interfaces agreed at a site meeting between contractors and designer. The existing depot building will become a site office for the groundworks and car park extension works commencing 20th July.Read more


TransWilts meet with contractors on Site

After lease signature, our first site visit was held with our contracting team on 3rd July. This was an opportunity to finalise some plan details and agree a work programme. Based on this preliminary visit we expect to start on site 20th July and open the south car park with the new electric car charger spaces on 1st August. Read more