Contractors meet with Designer to finalise work scope 20th July to 28th August

Final measurements made and interfaces agreed at a site meeting between contractors and designer. The existing depot building will become a site office for the groundworks and car park extension works commencing 20th July. Our car park provider will begin installation of the cctv and payment machines on 27th July – car park charging is planned to be introduced from 31st July. Our target completion for this work phase is 28th August.

Refurbishment of the depot building into the café will follow on under a separate contract which is yet to be awarded.