The month of October shows the substantial progress that has been made with most of the car park and exterior work now completed. Refurbishment of the cafe building interior shell is almost complete with brand new services, double glazed windows and doors. Our contractors have done a fantastic job!

Exterior: The ramp and access to the extended car park is complete and cycle racks installed. Lighting and CCTV is working. The extended car park is not accessible for cars until the existing facility becomes more full. Train passenger numbers remain low although a two hourly service is operational.

Interior: The cafe interior has a brand new multi access toilet. We expect to start kitchen fitment in November/December with the cafe opening in the spring. All cafe plans will be subject to the Coronavirus situation in 2021 but we are planning for exterior seating when the spring weather arrives.

Car Parking: The car parking payment systems are fully operational with both payment machine and pay by phone RingGo already being used.

E-Charging: Two spaces for electric car charging are installed waiting for the power supply connection but should be active in November.